- 05SC Icelandic River and Washow Bay Creek
ICELANDIC RIVER AND WASHOW BAY CREEK
INTEGRATED WATERSHED MANAGEMENT PLAN
 |
 |
|
The Icelandic River and Washow Bay Creek (05SC) IWMP was initiated in March of 2006 and a final version of the plan is available HERE. The process included the following steps:
- Compile available scientific data for the watershed (May 2006 – Feb 2007)
- Host community meetings to receive public input on issues of concern (April 18, 2007)
-
Establish watershed a list of action items as well as resource goals and objectives based on community issues. (May 2007- March 2009)
-
Summary issue document available here.
-
Host second public meeting to review a draft version of the plan
-
Revise and submit plan to Manitoba Water Stewardship for approval by Minister Melnick
-
Conduct programming that meets watershed needs and community issues (May 2009 – May 2017)
- Monitor success based on goals and objects (May 2009 – May 2017)
-
Revise plan in 8 years (May 2017)
In May of 2006 the technical watershed planning advisory team (WPAT) met to discuss the watershed planning process and available information for the 05SC watershed.
|
The following includes the technical submissions received from WPAT members:
|
|
The following includes maps developed by the EICD and received from WPAT members:
|
Information about the watershed is available in a Watershed Characterization document which can be downloaded HERE
|